Aristo Construction Update

We’re almost finished the shoring and excavation phase at Aristo. Shoring is 100% complete and excavation is at 95%. The crane on the south side of the site is currently being installed. Waterproofing of the perimeter walls and installation of concrete footings, part of the building’s foundation, have started.