We’re almost finished the shoring and excavation phase at Aristo. Shoring is 100% complete and excavation is at 95%. The crane on the south side of the site is currently being installed. Waterproofing of the perimeter walls and installation of concrete footings, part of the building’s foundation, have started.
Be sure to follow Facebook and Twitter for even more information.
Click on the “PLAY” arrow to join the on-site action and watch the professional teams that are literally shaping the things to come at your new home and community.
