West Village logoConstruction is progressing nicely at West Village, in Etobicoke.

At Tower 1, we are working up out of the ground with the ground floor concrete 80% poured. The precast installation is expected to begin this fall.

The site at West Village.

The site at West Village.

At West Village Tower 2, we are still working on the below ground concrete. The walls and slabs of the P3 level of the underground garage are 80% complete and of the P2 level 50% complete.

For information on suites available at West Village visit the presentation centre or call 416-620-1887.