Concrete Pour for P1 Parking Level In Progress at Trio

November 2016 Construction Update The concrete pour for the P1 parking level is in progress at the Trio community along with the plumbing and electrical rough-in work. Our Project Management team at the same time is working on the tendering process for the community. Design appointments are currently taking place for the 9th floor. Follow […]

Concrete Being Poured on the Mechanical Penthouse Level at Aqualina

November 2016 Construction Update Concrete is currently being poured on the mechanical penthouse level at the Aqualina community. Windows are being installed on the 10th floor and suite channeling is on the 2nd floor. Terraces located on the 3rd floor are in the waterproofing process while cladding of the steel architectural columns has begun. Follow […]

Concrete Pour for Ground Floor is 100% Complete at Alter

November 2016 Construction Update The concrete pour for the ground floor is 100% complete at the Alter community with the mezzanine floor at 25% complete. The construction team anticipates the start of window installations mid-winter. Follow us on Facebook and Twitter for even more information. Interested in purchasing? Visit our Presentation Centre for more information. Click […]

Drywall is currently being installed on the 42nd floor at Alto and Parkside.

November 2016 Construction Update Drywall is currently being installed on the 42nd floor at Alto and Parkside. Interior finishes are 50% complete within the Alto building and mechanical and electrical rough-in work is happening on the 43rd floor. Closings are taking place on the 9th floor within the Alto building while Homeowner Orientations are taking […]

Concrete Being Poured on the 7th Floor at Sherwood

November 2016 Construction Update Concrete is currently being poured on the 6th and 7th floors at Sherwood at Huntington. The construction team anticipates the completion of the concrete pour by the end of this year and the commencement of precast (the exterior skin of the building) in the New Year. Follow us on Facebook and […]

Construction Anticipated to Start in the New Year for Avani 2

November 2016 Construction Update Building permit drawings have been submitted to the city on November 10th, 2016 for the Avani 2 community with the anticipated start of construction in the New Year. Follow up on Facebook and Twitter for even more information. Interested in purchasing? Visit our Presentation Centre for more information. Click on the […]

Final Occupancy Inspections Taking Place at Avani

November 2016 Construction Update The paperwork for registration of the Avani community is currently being reviewed by the city. Registration approval is anticipated for the end of this year with Final Closings taking place mid to late winter. Our on-site construction team is preparing for the final inspection of occupancy permits for the hoist suites […]