The holidays are over, decorations have been put away and visiting family and friends have returned to their daily routines….. It’s that time of year again, when many of us flee the frigid temperatures and head to warmer climates. While the condominium lifestyle has a lot of benefits, (warm amenities to enjoy so close to […]

Concrete Pour for P1 Parking Level In Progress at Trio

November 2016 Construction Update The concrete pour for the P1 parking level is in progress at the Trio community along with the plumbing and electrical rough-in work. Our Project Management team at the same time is working on the tendering process for the community. Design appointments are currently taking place for the 9th floor. Follow […]

Drywall is currently being installed on the 42nd floor at Alto and Parkside.

November 2016 Construction Update Drywall is currently being installed on the 42nd floor at Alto and Parkside. Interior finishes are 50% complete within the Alto building and mechanical and electrical rough-in work is happening on the 43rd floor. Closings are taking place on the 9th floor within the Alto building while Homeowner Orientations are taking […]

The “Perfect” Shops for your “Parfait” Home.

While North York may not be your first destination when you’re looking for those funky and / or fabulous furniture statement pieces (you know the ones, those extraordinary pieces that lift a room and make your friends wondrously envious), we found some hidden gems! After doing a little investigative shopping, we’ve discovered a few select stores that […]

P3 Level Pour Almost Complete at Trio at Atria

October 2016 Construction Update. The P3 parking level is 90% complete with the concrete pour at the Trio community. Production has started for the precast panels, the exterior skin of the building, and windows are anticipated to start production at the end of this year.

Kitchens Being Installed on the 25th Floor at Alto and Parkside

Drywall is currently being installed on the 37th floor at the Alto and Parkside community. Tile installations are on the 27th & 28th floors, kitchens on the 25th, granite countertops on the 22nd and flooring on the 18th floor.

Alto and Parkside at Atria September 2016 Construction Update

Drywall is currently being installed on the 33rd floor at the Alto and Parkside community. Tile installations are on the 22nd floor, kitchens are on the 19th, and laminate flooring is on the 13th floor.

The Best Part of my Job

Guest blog post from Real Condo Life: Sometimes the best part of being in the condo development business is actually getting on site. Okay – often the best part. Today was one of those days. And it’s beyond “often”… it’s always, that you walk away with a tremendous appreciation, respect and pride, for all of […]

Model Suites Open at our Atria Community

Beautifully Appointed Model Suites Now Open If you haven’t yet visited our Model Suites at Alto & Parkside at Atria, you may want to make an appointment!  These beautifully designed and finished suites are attracting a lot of attention! “Suite 115 is a one bedroom with den,” says Sales Representative Tara Stone. “It has a spacious open […]