Argento March Construction Update

Shoring and excavation continue at Argento with the construction teams having made progress to the P4 level of the parking garage. A permit application for dewatering is in with the city and the Toronto Conservation Authority. Once the teams work … Continue reading

Share
Posted in Condo Construction, North York Condos | Tagged , , , , , , , , , | Comments Off

Ventus Phase 2 March 2013 Construction Update

Municipal occupancy inspections will commence on March 26th for the 22nd floor up to the Penthouse level. Once these permits are received, only the hoist suites will remain in order for the community to achieve full occupancy. Our construction trades … Continue reading

Share
Posted in Condo Construction, Scarborough Condos | Tagged , , , , , , , , , , , , , | Comments Off

Aristo March 2013 Construction Update

The Aristo community is reaching ever higher as the sixth floor of Aristo Tower 1 and the third floor of Tower 2 are both 100% complete. The precast panels which will be the skin of the community are still in … Continue reading

Share
Posted in Condo Construction, North York Condos | Tagged , , , , , , , , , , | Comments Off

Ventus 1 Customer Care Office is Moving

On Thursday, March 28, 2013 the Ventus Phase 1 Customer Care office in suite 306 will be merging with the Ventus Phase 2 Customer Care office located in suite 315. All contact information will remain the same but the service … Continue reading

Share
Posted in Condo Construction, Customer Care, Scarborough Condos | Tagged , , , , , , , , , , , | Comments Off

300 Front Street West – February 2013 Construction Update

The concrete pour at 300 Front is almost complete. Our construction teams are now pouring on the 47th floor (out of a total of 49 floors). Interior finishes such as windows are being installed on the 37th floor, drywall on … Continue reading

Share
Posted in Condo Construction, Downtown Toronto Condos, Toronto Condos | Tagged , , , , , , , , , , , | 2 Comments

Atria February 2013 Construction Update

Our construction teams are working hard to prepare the land for excavation. Road remediation is complete and we are now waiting on land conveyance to start the construction of the road leading to the community. The installation of temporary power … Continue reading

Share
Posted in Condo Construction, North York Condos, Uncategorized | Tagged , , , , , , , , , , | Comments Off

Blythwood February 2013 Construction Update

The concrete pour at Blythwood is almost complete with our construction teams now pouring on the 8th floor (out of a total of 9 floors). Plumbing and electrical rough-ins are continuing installations on the 7th and 8th floors and precast … Continue reading

Share
Posted in Condo Construction, Toronto Condos | Tagged , , , , , , , , , , , | Comments Off

West Village February 2013 Construction Update

The West Village Towers are steadily getting taller with our teams now pouring concrete on the 25th floor for West Village Tower 1 and the 16th floor for West Village Tower 2. The precast for Tower 1 is now complete … Continue reading

Share
Posted in Condo Construction, Etobicoke Condos | Tagged , , , , , , , , | Comments Off

Aristo February Construction Update

Concrete forming at Aristo at Avonshire is in full swing, the third floor of Aristo Tower 1 is 90% complete and the forming for the second floor for Tower 2 is 100% complete. The precast panels which will be the … Continue reading

Share
Posted in Condo Construction, North York Condos | Tagged , , , , , , , , , , | Comments Off

300 Front Street West construction

Every once in a while it’s nice to see the world through a younger person’s lens. Here are a few construction shots of Tridel’s 300 Front Street West taken January 24, 2013 by photographer, Skyler Graham, a photography student at … Continue reading

Share
Posted in Condo Construction, Downtown Toronto Condos | Tagged , | Comments Off