Community Progress Update – December 2017

The concrete pour and window installations have been completed at the 101 Erskine community. The on-site construction team is progressing with the wall framing for suites on the 30th floor and drywall on the 23rd. Installation of the interior finishes is occurring throughout the building with tile work on the 14th floor, kitchen cabinetry on the 12th and flooring on the 8th. In addition to this work, plumbing and electrical work is taking place on the 2nd floor.

At this time our teams have started working on the exterior landscape of the community and the lobby has reached 80% completion.