Live Construction Camera

July 2019 Construction Update

The teams at Aquabella have completed the formwork on the P1 garage level and are continuing on the mezzanine level. Mechanical and electrical work is currently in progress within the garage parking levels. The ground floor slab is 35% completed and the construction of the walls on ground floor have commenced.

Interested in more Aquabella construction updates? Check back frequently to hear from our team!

Communications Plan & Contacts

Questions regarding the Via Bloor community and your suite?

Tridel’s C3 Centre
Customer Connection Centre

Fast & Easy because answers shouldn’t be hard to find.

Email: ask@tridel.com | Phone: 416.661.9394

Projected Construction Timing

Activity Estimated Start** Estimated Completion** Duration**
Shoring/Excavation March 2018 October 2018 7 Months
Forming September 2018 March 2020 18 Months
Building Envelope October 2019 April 2020 6 Months
Interior Finishing November 2019 October 2020 11 Months
Streetscaping October 2020 March 2021 5 months
Occupancies October 2020 April 2021 6 Months

 

**Dates are tentative and subject to change without notice.
Hoarding and overhead protection to be removed throughout streetscaping activities; current forecasted removal is between October 2020 to March 2021.