Construction Progress Update – January 2019

Aquavista at Bayside began with the first Homeowner Orientation (HOO) on January 8, 2019. Typically lasting approximately two hours, the HOO, also known as a Pre-Delivery Inspection or PDI, is a new homeowner’s first opportunity to view their completed home. While HOO appointments have begun on the lower floors, the on-site Construction team continues work on the higher floors of the community. Currently, carpeting is being laid in the third floor corridors and flooring is being installed in suites on the 6th floor. Drywall has been completed up to the 11th and the tradespeople are now working to enclose the walls of the suites on the floors above. Outside, landscaping work on the second floor terrace has been progressing well.


Photos updated every 30 minutes during work hours.

Contacts

Questions regarding the Via Bloor community and your suite?

Tridel’s C3 Centre
Customer Connection Centre

Fast & Easy because answers shouldn’t be hard to find.

Email: ask@tridel.com | Phone: 416.661.9394

Projected Construction Timing

Activity Estimated Start** Estimated Completion** Duration**
Shoring/Excavation Complete Complete
Forming Complete Complete
Building Envelope November 2017 September 2018 10 Months
Interior Finishing May 2018 July 2019 16 Months
Streetscaping July 2018 October 2018 3 months
Occupancies January 2019 July 2019 6 Months

 

**Dates are tentative and subject to change without notice.
Hoarding and overhead protection to be removed throughout streetscaping activities; current forecasted removal is November of 2018.