Construction Updates & Live Camera

July 2021 Construction Update

Construction at the Bianca community is progressing well with forming and precast installation now complete. The teams are fitting the last few windows on the upper floors to finish the exterior walls of the building, or what is known as the ‘building envelope’. This is an exciting milestone as it means homeowners are one step closer to moving into their new home.

We have begun interior finishing in the suites, with mechanical and electrical work progressing on floor 6. The teams are installing drywall in the ground floor common amenity spaces for the community and have also started the exterior landscaping, which we anticipate being done by the fall or early winter.

The next major milestone for Bianca will be when we prepare to welcome homeowners to the community for their Homeowner Orientations (or PDIs).

We will continue to update you throughout this project and let you know if our schedules change. Please check this page regularly.

Live From Bianca
Check back often to see live progress from our on-site construction feed which is updated every 15 minutes.


Photos updated every 15 minutes during work hours.

Bianca Construction Management Plan & Community Communication Strategy

The Bianca community is located at the north-east corner of Albany Avenue and Dupont Street in the City of Toronto. The proposed development includes 216 residential units and 2,194m2 of commercial retail.

The following information is considered in this report:

  • Construction activity sequence and schedule;
  • Construction vehicle routes, access and material lay-down needs;
  • Construction staff parking strategy;
  • Traffic operations, safety and street maintenance;
  • Resident communications strategy.

Contact Us

Questions regarding the Bianca community and your suite?

Tridel’s C3 Centre
Customer Connection Centre

Fast & Easy because answers shouldn’t be hard to find.

Email: ask@tridel.com | Phone: 416.661.9394

Projected Construction Timing

Activity Estimated Start** Estimated Completion** Duration**
Shoring/Excavation October 2018 June 2019 8 Months
Forming June 2019 September 2020 12 Months
Building Envelope May 2020 November 2020 6 Months
Interior Finishing September 2020 July 2021 10 Months
Streetscaping November 2020 March 2021 4 Months
Occupancies March 2021 August 2021 5 Months

 

**Dates are tentative and subject to change without notice.