Homeowner Orientations Begin at Aquavista at Bayside

  January 2019 Construction Update At Aquavista at Bayside, the second phase of the Hines and Tridel luxury waterfront community, construction has been progressing well.  Since construction began in January 2016, the building has reached it’s full height of 12 stories and the community celebrated their “rooftop” milestone in December of 2017.   Homeowner Inspections […]

Parfait at Atria January 2019 Construction Update.

  Construction progress at this sweet North York Community. Over near Sheppard Avenue and Victoria Park in North York, construction on the fourth and final phase of the Atria community – Parfait – continues. The on-site teams are working on the verticals of the 3rd and 4th floors.  Verticals are the “vertical” pillars that support the floor above.  […]

Islington Terrace Rises In Etobicoke

  Islington Terrace Construction Update Islington Terrace, located near Bloor and Islington in Toronto’s west end, has now reached its full height of 45 storeys. If you have never watched the construction of a new community, here’s a simplified explanation of how its done:  First, the structure is built one floor at a time, moving upwards.  […]

Getting our Footing at Aquabella at Bayside

The November 2018 Construction Update While it might not look like a lot is happening, behind the construction hoarding and work trucks, construction at Aquabella at Bayside is progressing nicely.  Currently, the on-site team is forming footing caps, vertical columns and walls on the P4 to P3 levels.  Once footings are complete, work on the […]

Forming at FORM

  The November 2018 Construction Update The FORM community is progressing well, with the on-site team now forming the eleventh floor.  Forming entails laying out the actual structural components of each floor slab and vertical (the walls and columns) component.  Once all of the components are in place, concrete is poured over-top, securing them in […]

Shoring and Excavation Begin at Scala – November 2018 Construction Update

  Pre-Construction Development Located just north of Leslie and Sheppard, the Scala community has been bustling with preparation activities.   The site, encompassing approximately 6.5 acres, has been undergoing a lengthy but necessary list of changes in preparation of redevelopment, ranging from demolition, regrading of the site, and more.   New Road and Services The roads that will […]

Construction Begins at Bianca on The New Dupont

Construction of Bianca Has Begun We are very pleased to announce the start of construction at Bianca, located on The New Dupont, just west of Spadina.  With the completion of demolition of the existing on-site structures, the next phase of development is ready to begin.         Site Mobilization The first step is […]

Putting Up Tower Cranes at Via Bloor 1 & 2

September 2018 Construction Update We are excited to announce that we will start putting up the tower cranes at our Via Bloor community in the next several weeks. During this time, there will be added activity and noise on site during the installation. This process will take approximately two weeks from beginning to end, as [...]

7th Floor Being Poured at SQ2 at Alexandra Park

September 2018 Construction Update The SQ2 community is moving along well with the Construction teams currently pouring the 7th floor slab. Window installation has started, beginning with the ground floor. The underground connections for water, storm, and sanitary sewers for the community are now complete. Also, the studs that will form the exterior walls of [...]

Shoring Complete at Selene at Metrogate

Construction is progressing well at our Selene at Metrogate community.  Currently, shoring work is finished and 95% of the the excavation process is complete. Bathtubbing The Tower The next step is to begin the underground waterproofing process, also known as ‘bathtubbing’ the building.  The first step is to pour a concrete base – known as the […]