Parfait With a Cherry On Top – The August 2019 Construction Update

Parfait With a Cherry On Top – The August 2019 Construction Update

Parfait at Atria has now reached its full height of 19 storeys.

North York’s sweetest condominium is rising fast!  In fact, Parfait now rises 19 storeys into the North York skyline.

The onsite construction teams are currently working on completing forming of the Mechanical Penthouse, which sits on the top of the building.  Additionally, work on the exterior building envelope is underway.  This includes the finishing of masonry, precast and window installations.

Parfait at Atria

Next Steps – Enclosing the Building

In the underground parking levels, both mechanical and electrical rough-ins are being installed.  This includes the conduits or “tubes” which will house the electrical wiring and plumbing systems.  Meanwhile, work on the exterior wall channeling and board are underway.  Simply put, construction is currently working on enclosing the building and have started the process of installing the exterior walls of these future homes.

About Parfait

Once complete, Parfait at Atria will be home to 235 suites.  Conveniently located near Highways 401, 404 and the DVP, Parfait is the final phase of the successful Atria community in North York.