August Construction Update

Our on-site construction teams are currently installing the precast for the Sherwood community on the 7th and 8th floors, while window installations are in progress on the 7th.

In-suite drywall is complete up to the 3rd floor and the teams are working on finishing the brickwork for the exterior wall of the community. The plumbing and electrical rough-ins are currently being done on the 2nd floor.

We will continue to send you updates, but follow Facebook and Twitter for even more information.