In December of 2014 we started the construction process for the SQ at Alexandra Park community. To date, our construction team has completed all excavation work and is about 15% complete with the concrete pour. The ground floor slab is currently being formed.

We will continue to send you updates, but follow us on Facebook and Twitter for even more information.

Click on the image below for photo updates. The SQ construction site is located adjacent to the Toronto Community Housing Townhome project seen below.