West Village Construction Update

At West Village Tower 1, the excavation phase is complete and we are now coming out of the ground. Pouring of the remaining sections of the garage walls and slabs is continuing, with P2 level 80% finished, P1, 50% and the ground floor, 20%. The precast installation is expected to begin early Fall. At West […]


Blythwood at Huntington Construction Update

We are on the way up at Blythwood at Huntington! Excavation is 90% complete and then we will move to the footings which form a major part of your community’s building foundation. It is a really exciting time as we now begin to literally move-up with our construction and by the end of June we […]


Hullmark Centre Construction Update

At Hullmark Centre, concrete has been poured up to the 5th floor of the south tower and the 2nd floor of the north tower. Plumbing and electrical system installation has started in the underground garage. The north TTC tunnel foundations are currently being put in and window installation is expected to begin next month. Be […]


300 Front Street Construction Update

300 Front Street West is continuing to rise and make a fantastic statement at the corner of Front and John. Concrete is being poured on the 16th floor and windows have been installed to the 10th floor. Plumbing and electrical has been roughed in up to the 8th floor and drywall has begun on the […]


Parc Nuvo Construction Update

 We are pleased to report that Parc Nuvo now has occupancy up to the 18th floor. Interior finishes, plumbing and electrical systems are currently being installed on the “upper floors,” 19 through 36. Parc Nuvo is also currently aiming for LEED® Gold certification. Be sure to follow Facebook and Twitter for even more information in […]


Blythwood at Huntington – two new suites added 1B+D and 2U+D

High-end living in a gorgeous boutique community, nestled beside a natural ravine. Homeowners are going to love living at Blythwood at Huntington, Bayview south of Lawrence. We are pleased to now offer a one bedroom plus den suite to complement our more spacious homes. “This now means that those clients who have come in looking […]


Avani Construction Update

        We are working on construction drawings at Avani and submitting for the permit this summer. The neighbourhood that Avani is in, Metrogate, has been certified LEED® Silver in the new Neighbourhood Development program. Follow Facebook and Twitter for even more information.  


101 Erskine renderings released

The parking lot was jam packed at Tridel Head Office yesterday, strange because it was a Sunday. The reason for all the activity? 101 Erskine brochures and price lists were available for pick up! For those who were unable to make it, the brochure is now available in a digital version here. And the fantastic […]


Argento Construction Update

 We are very excited that construction has started at Argento. Shoring, which is a support system to hold back earth during excavation, and the drilling of piles, the post-like foundations, began on May 29th. Excavation is expected to begin toward the end of July. The construction footings, which are part of the foundations, should start […]


Atria Construction Update

With each day, we’re getting closer and closer to building your new community! We are expecting that construction of Atria will begin this fall, pending approval of the Site Plan Application. Alto and Parkside will be going up at the same time. As Atria is a Built Green Built for Life® community, it will be […]