Construction Updates & Live Camera

July 2020 Construction Update

With interim occupancies beginning this month, we are thrilled to announce that we have begun to welcome our homeowners to the Bloorvista community. Our Customer Care team is currently conducting Pre-Delivery Inspections for suites on the 11th floor.

The steps of the Grand Staircase on Cordova have opened this month, providing access from Islington to Cordova Stairs. We anticipate the Staircase and ramp to be fully completed by late summer.

Interested in more Bloorvista construction updates? Check back frequently to hear from our team!

Live From Bloorvista
Check back often to see live progress from our on-site construction feed.

Contacts

Questions regarding the Bloorvista community and your suite?

Tridel’s C3 Centre
Customer Connection Centre

Fast & Easy because answers shouldn’t be hard to find.

Email: ask@tridel.com | Phone: 416.661.9394

Projected Construction Timing

Activity Estimated Start** Estimated Completion** Duration**
Shoring/Excavation July 2017 October 2017 4 Months
Forming September 2017 May 2019 21 Months
Building Envelope August 2018 November 2019 16 Months
Interior Finishing January 2019 June 2020 18 Months
Streetscaping July 2019 December 2019 6 months
Occupancies October 2019 May 2020 8 Months

 

**Dates are tentative and subject to change without notice.
Hoarding and overhead protection to be removed throughout streetscaping activities; current forecasted removal is between July 2019 and December 2019.