Live Construction Camera & Updates

Community Progress Update – September 2018

Construction at the Form community is moving along well. With all underground levels complete, the teams are currently pouring concrete to form the 2nd floor. Precast, the exterior facade of the building, and window installation is anticipated to begin this fall. Our Design Consultants have completed most Design & Décor appointments for the community, with handheld showers and window coverings being amongst the most popular upgrades and finishes.

Photos updated every 30 minutes during working hours

Contacts

Questions regarding the FORM community and your suite?

Tridel’s C3 Centre
Customer Connection Centre

Fast & Easy because answers shouldn’t be hard to find.

Email: ask@tridel.com | Phone: 416.661.9394

Projected Construction Timing

Activity Estimated Start** Estimated Completion** Duration**
Shoring/Excavation June 2017 December 2017 7 Months
Forming December 2017 December 2018 12 Months
Building Envelope Fall 2018 Spring 2019 7 Months
Interior Finishing Winter 2018 Spring 2019 5 Months
Streetscaping Spring 2019 Spring 2019  1 Month
Occupancies July 2019 September 2019 3 Months

 

**Dates are tentative and subject to change without notice.
Hoarding and overhead protection to be removed throughout streetscaping activities; current forecasted removal is spring of 2019.