Construction Updates

Congratulations!

You may have moved into your new home or your moving day is just around the corner. It’s an exciting time and we want to make sure you’re prepared.

If you haven’t moved in yet, you will meet our Customer Care team for your Home Orientation appointment, which is the first time you will see your new home and community. These appointments are currently taking place. To help you prepare for your appointment, take some time to read your Welcome Home guide. It contains important information about moving in, your home warranty and requesting service from our team. Your Guide to Moving In may also provide some helpful information as you prepare for your big day.

If you’ve moved into your new home, we also recommend that you read your Homecare Guide, which provides you valuable tips on how to properly maintain your new home and protect your investment.

Learn more about your community

Live From Islington Terrace

Check back often to see live progress from our on-site construction feed.

Contact Us

Questions regarding the Islington Terrace community and your suite?

Tridel’s C3 Centre
Customer Connection Centre

Fast & Easy because answers shouldn’t be hard to find.

Email: ask@tridel.com | Phone: 416.661.9394

Projected Construction Timing

Activity Estimated Start** Estimated Completion** Duration**
Shoring/Excavation July 2016 February 2017 7 Months
Forming February 2017 February 2019 26 Months
Building Envelope April 2018 September 2019 20 Months
Interior Finishing June 2018 April 2020 26 Months
Streetscaping April 2019 September 2019 6 months
Occupancies May 2019 March 2020 10 Months

 

**Dates are tentative and subject to change without notice.
Hoarding and overhead protection to be removed throughout streetscaping activities; current forecasted removal is between April 2019 and September 2019.