Construction Updates & Live Camera

December 2020 Construction Update

With construction at the Scala community well underway, we are excited to let you know that we have completed the forming of concrete up to the 7th floor. Our construction teams are currently progressing on the building envelope, with the installation of precast and windows.

We will start installing drywall and working on the streetscaping in early 2021. The next major milestone to follow will be when we reach the roof and top off the building.

We will continue to update you throughout this project and let you know if our schedules change. Please check this page regularly.

Live From SCALA
Check back often to see live progress from our on-site construction feed.

Contact Us

Questions regarding the Scala community and your suite?

Tridel’s C3 Centre
Customer Connection Centre

Fast & Easy because answers shouldn’t be hard to find.

Email: ask@tridel.com | Phone: 416.661.9394

Projected Construction Timing

Activity Estimated Start** Estimated Completion** Duration**
Shoring/Excavation October 2018 June 2019 7 Months
Forming March 2019 December 2020 21 Months
Building Envelope April 2020 March 2021 11 Months
Interior Finishing November 2020 January 2022 14 Months
Streetscaping March 2021 July 2021 4 months
Occupancies January 2022 August 2022 6 Months

**Dates are tentative and subject to change without notice.