December 2020 Construction Update
With construction at the Scala community well underway, we are excited to let you know that we have completed the forming of concrete up to the 7th floor. Our construction teams are currently progressing on the building envelope, with the installation of precast and windows.
We will start installing drywall and working on the streetscaping in early 2021. The next major milestone to follow will be when we reach the roof and top off the building.
We will continue to update you throughout this project and let you know if our schedules change. Please check this page regularly.

Live From SCALA
Check back often to see live progress from our on-site construction feed.
Contact Us
Questions regarding the Scala community and your suite?
Tridel’s C3 Centre
Customer Connection Centre
Fast & Easy because answers shouldn’t be hard to find.
Email: ask@tridel.com | Phone: 416.661.9394
Projected Construction Timing
Activity | Estimated Start** | Estimated Completion** | Duration** |
Shoring/Excavation | October 2018 | June 2019 | 7 Months |
Forming | March 2019 | December 2020 | 21 Months |
Building Envelope | April 2020 | March 2021 | 11 Months |
Interior Finishing | November 2020 | January 2022 | 14 Months |
Streetscaping | March 2021 | July 2021 | 4 months |
Occupancies | January 2022 | August 2022 | 6 Months |
**Dates are tentative and subject to change without notice.