Construction Updates

June 2021 Construction Update

Construction at the Via Bloor community is progressing well with forming complete as the teams have reached the roof for both Via Bloor 1 and Via Bloor 2. This is an exciting milestone as it means homeowners are one step closer to moving into their new home.

Precast is 95% complete, and window installation is on the 36th floor of Via Bloor 1 and on the 43rd floor of Via Bloor 2. In-suite interior finishing is well underway, with electrical, plumbing and ventilation rough-ins are in progress on the 26th floor for Via Bloor 1 and on the 28th floor for Via Bloor 2. Our teams are also installing drywall and painting is in progress on the lower floors of the community. Kitchen installation is on the 17th floor on Via Bloor 1 and on the 20th floor on Via Bloor 2. We will begin working on the streetscaping started June 2021.

We will continue to update you throughout this project and let you know if our schedules change. Please check this page regularly.

Live From Via Bloor
Check back often to see live progress from our on-site construction feed which is updated every 15 minutes.


Photos updated every 15 minutes during work hours.

Via Bloor Construction Management Plan & Community Communication Strategy

This strategy outlines the measures that will be taken before and during construction of the Via Bloor community located at 575 & 585 Bloor Street East. The community is situated on the south side of Bloor Street East, north of Howard Street, between Parliament Street and Edgedale Road.

Contact Us

Questions regarding the Via Bloor community and your suite?

Tridel’s C3 Centre
Customer Connection Centre

Fast & Easy because answers shouldn’t be hard to find.

Email: ask@tridel.com | Phone: 416.661.9394

Projected Construction Timing

Activity Estimated Start** Estimated Completion** Duration**
Shoring/Excavation February 2018 November 2018 10 Months
Forming October 2018 December 2020 27 Months
Building Envelope April 2020 April 2021 12 Months
Interior Finishing August 2020 October 2021 14 Months
Streetscaping January 2012 July 2021 7 Months
Occupancies July 2021 February 2021 8 Months

 

**Dates are tentative and subject to change without notice.
Hoarding and overhead protection to be removed throughout streetscaping activities; current forecasted removal is between July 2020 to Dec 2020.