Community Updates

February 8 2018 Community Update

As you may have noticed, the Via Bloor site is currently enclosed with temporary fencing.

Our construction management plan was approved by the Toronto & East York Community Council on January 16, 2018, which allowed us to obtain our final hoarding permit. As such, the existing temporary fencing will now be repositioned to sit at the location where the permanent fencing will eventually be installed. Hoarding is necessary to ensure the site is secure and safe for you, your neighbourhood and us. The process of moving the temporary fencing will begin at the end of this week or early next, while the permanent hoarding structure is scheduled to be installed by early March.

You will further notice that the hoarding will close off the northern Howard Street sidewalk while also encroaching slightly onto Howard Street. This encroachment will not affect regular vehicular traffic.

In addition, with construction officially starting at the Via Bloor community, our Construction teams anticipate to begin shoring and excavation the week of February 19th. You may see a higher level of activity on the site, including the delivery of the equipment needed to complete this phase of the construction process.

Communications Plan & Contacts

Via Bloor Construction Management Plan & Community Communication Strategy

This strategy outlines the measures that will be taken before and during construction of the Via Bloor community located at 575 & 585 Bloor Street East. The community is situated on the south side of Bloor Street East, north of Howard Street, between Parliament Street and Edgedale Road.

Questions regarding the Via Bloor community and your suite?

Tridel’s C3 Centre
Customer Connection Centre

Fast & Easy because answers shouldn’t be hard to find.

Email: ask@tridel.com | Phone: 416.661.9394

For direct concerns surrounding the construction taking place, please contact:

Construction Site Office:
Tel: 416-996-9552
Hours: Mon-Fri, 7AM – 5PM
Security Dispatch:
Tel: 1-877-497-0125; or
416-477-3350 ext 0
Hours: 24 hours, 7 days a week
Deltera Construction Info:
Contact: Alex Gelman, Assistant Project Manager
Tel: 416-736-8353
Email: ReceptionC@tridel.com

Projected Construction Timing

Activity Estimated Start** Estimated Completion** Duration**
Shoring/Excavation February 2018 July 2018 5 Months
Forming July 2018 May 2020 23 Months
Building Envelope May 2019 August 2020 16 Months
Interior Finishing September 2019 October 2021 26 Months
Streetscaping August 2020 Jan 2021 6 months
Occupancies January 2021 October 2021 10 Months

 

**Dates are tentative and subject to change without notice.
Hoarding and overhead protection to be removed throughout streetscaping activities; current forecasted removal is between July 2020 to Dec 2020.